Laying of the new storm pipe is
nearly complete on the 4th Street leg of the project. The Hein
Construction crew is now concentrating on laying the pipe on a short leg on
7th Street west of Johnson Street. The weather has been very
cooperative allowing the sidewalk, driveway and landscaping crews to follow
closely behind the trenching crew. New grass is starting to sprout in the
construction zones that were seeded a couple weeks ago.
Beginning the week of October
10, the blacktopping crew will start laying asphalt on the streets that were
previously excavated. This will smooth out the bumps in those streets and
eliminate the dust caused by the gravel patches.